HOME   •    TEXT VERSION   •    CONTACT US

CONSTRUCTION

construction graphic


All other road closures can be found under our road closure page.

Please check the Niagara Region's web site for additional road works in the Niagara Area.

 

Construction Activity for Municipal Subdivisions and Niagara Region Projects
for the week of July 18, 2016

Municipal Construction Projects:

Project-

Empire Area Watermain Replacement and Sewer Separation (98% complete)

Location/
Description
To install watermain, watermain services and storm sewer for the Empire Area.
Activities Contractor has completed the deficiencies.
Project-

Clare Estates Phase 4/5 Work on South Pelham (80% complete)

Location/
Description
Removed existing road surface, replace/upgrade/install new underground infrastructure for Clare Estates Phases and new Sparrow Meadows developments
Activities Underground work complete, curbs installed, base asphalt in place
Project-

Clare Avenue Extension (70% complete)

Location/
Description
Clare Avenue extension between Lynbrook Lane and Webber Road for future development
Activities Various underground works, earth moving, grading. Watermain testing results received and passed. Two watermain connection commissioned.
Project-

Hansler Heights (Thorold) (80% complete)

Location/
Description
Various work being done on Hansler Road to accommodate new development in Thorold
Activities Underground infrastructure, road grading.
Project-

Roadway Resurfacing Program 2016 – Part 1 (98% Complete)

Location/
Description
  • Empire Street – East Main Street to York Street – Partial excavation, geogrid and granular base, curbs, sidewalk repair and full depth asphalt replacement.
  • Empire Street – York Street to Welland Street – Fill width milling of asphalt, sidewalk and curb repair and base repairs.
  • Eastwood Drive – Rice to Endicott – Sidewalk and curb repair, full depth asphalt replacement.
  • Westwood Crescent – Willson Road to Maureen Avenue – Sidewalk and curb repair, full depth asphalt replacement.
  • Humberstone Road – Full width asphalt reprocessing, granular top dressing, granular M shoulder, base repairs, and full depth asphalt replacement.
Activities Contractor is working on deficiencies this week.
One lane of traffic open at all times
Project-

Utility Cuts Final Reinstatement 2016 (97% Complete)

Location/
Description
Reinstating the utility cuts for the City of Welland.
Activities The contractor is working on the utility cuts
Project-

Hodgson Steel Sewer Separation (0% Complete)

Location/
Description
To install storm sewers on the Hodgson Steel Property.
Activities Project on hold.
Project-

Emulsion Tank Installation (99% Complete)

Location/
Description
99 Federal Road, Municipal Service Centre.
Activities Electrical work done to the pad. Pad is formed and concrete poured. 28 day curing process, before tank delivery. Tanks delivered and installed. Final ESA inspection to follow.
Project-

Energy Management – Lighting (70% Complete)

Location/
Description
Municipal Service Centre, Transit Garage, Civic Square
Activities Transit done. Currently in MSC. Civic yet to be done. To be completed July, 2016.
Project-

Wright Street Watermain Replacement and Road Rehabilitation (50% Complete)

Location/
Description
To install watermain, watermain services and road rehabilitation for Wright Street.
Activities Watermain has been commissioned. Contractor is installing the new water services this week.
Project-

Roadway Resurfacing Program 2016 – Part 2 (5% Complete)

Location/
Description
  • Rogers Drive – Niagara Street to Carlton Avenue – Full excavation, granular base, curbs, sidewalk and full depth asphalt replacement.
  • Victoria Street – Hellems Avenue to Burgar Street – Full width milling of asphalt, sidewalk and curb repairs and base repairs. Also lead service replacements.
  • Burgar Street – Division Street to Victoria Street (North Limit) – Full-width milling, sidewalk and curb repair, base repairs, asphalt replacement. Also lead service replacements.
  • Burgar Street – Victoria Street (North Limit) to Lincoln Street – Sidewalk repair, Full length curb replacement, and full depth asphalt replacement. Also lead service replacements.
  • River Road – Ross Street Intersection - Full excavation, granular base, curb, and full depth asphalt replacement.
Activities The contractor is working on the road works for Rogers Drive this week.
Project-

Niagara Street Watermain Replacement and Road Rehabilitation (0% Complete)

Location/
Description
To install watermain, watermain services and road rehabilitation for Niagara Street from Riverbank to Thorold Road.
Activities To start construction by early August, 2016.
Project-

675 Tanguay Avenue (90% Complete)

Location/
Description
Private Water Service for development.
Activities Water Service was commissioned.
Project-

Sparrow Meadows Subdivision (80% Complete)

Location/
Description
To install watermain for South Pelham and Julia for development.
Activities Watermain completed. To receive the water sample results this week.

 

Other Construction Projects:

Bridges Close For Improvements

Niagara Region will undertake a complete replacement of the Beaverdams Road Bridge (Located On Beaverdams Rd., Thorold) and the Power Canal Bridge (Located on Merrittville Hwy. Thorold) commencing on Monday, March 30, 2015 until August 2016. For more information please click here.