All other road closures can be found under our road closure page.
| Project- |
River Road Storm Sewer and Roadway Construction between Ross Street and Woodlawn Road (99% Complete) |
| Location/ Description |
Construction of a new storm sewer on River Road for service of future Sportsplex complex and urbanized road cross-section. |
| Activities | none. |
| Project- |
East Main Street Watermain Replacement and Sanitary Sewer Abandonment (99% Complete) |
| Location/ Description |
Watermain installation on East Main Street between Ross Street and Golden Boulevard East. Sanitary sewer abandonment on East Main Street between Scholfield Avenue and Golden Boulevard East. |
| Activities | Remaining deficiencies have been completed. |
| Project- |
Sanitary Sewer Service Lateral Replacement Program 2012 (95% Complete) |
| Location/ Description |
Cured in-place rehabilitation or open-cut replacement of deficient sanitary laterals within the municipal right-of-way. Various locations. |
| Activities | Final open-cut replacement to proceed when weather is favourable. |
| Project- |
Road Reconstruction, Resurfacing and Urbanization Program 2012 (92% Complete) |
| Location/ Description |
- Elmwood Avenue between Lincoln Street and Windsor Drive - Urbanization, reconstruction and sidewalk repairs; - Woodlawn Cemetery reconstruction of driveways near Niagara Street; - Lincoln Street between Prince Charles Drive and King Street (excluding the bridge spanning the WRCC) - Resurfacing and sidewalk repairs; - Clare Avenue between Heritage Lane and the Northern City Limits Storm sewer construction, partial urbanization (west side) and reconstruction; - Broadway between St. George Street and Riverside Drive - Resurfacing and sidewalk repairs; - King Street - Partial resurfacing of between Lincoln Street and State Street; - Myrtle Avenue between Cohoe Street and Major Street Surface surface asphalt placement; - Prince Charles Drive between Riverside Drive and Maple Avenue - New sidewalk |
| Activities | - Elmwood Avenue: Surface asphalt to be completed in mid-June.
- Woodlawn Cemetery: Complete. - Lincoln Street: Complete. - Broadway: Landscaping underway. Milling (east end), surface asphalt and remaining landscaping to resume in early June. - King Street: Deferred (Scope of work and budget to be re-examined) - Myrtle Ave: Complete - Prince Charles Drive: Complete |
| Project- |
Gordon School (468 Thorold Road) |
| Location/ Description |
Site plan development |
| Activities | Water and storm connections completed. Final road restoration remaining. |
| Project- |
Diamond Trail Public School (315 Southworth St) |
| Location/ Description |
Site plan development |
| Activities | Water connection complete. Sanitary sewer lateral to be constructed following investigation. |
| Project- |
Medical Building (555 Prince Charles Drive) |
| Location/ Description |
Site plan development |
| Activities | Municipal site servicing (water, storm and sanitary) .Water testing to proceed upon notice. |
| Project- |
Utility Cut Final Reinstatement Program 2012/2013 ( 40% Complete) |
| Location/ Description |
Final reinstatement of roads, sidewalks, curb and boulevards following previous years excavations. |
| Activities | Concrete, asphalt and landscaping work underway. |
| Project- |
Welland International Flatwater Centre (WIFC) |
| Location/ Description |
Site servicing (water service and sewer forcemain) |
| Activities | Inspection of water service and sanitary forcemain. |
| Project- |
OAW- Lincoln Street Drainage Area I/I Investigation - Lincoln Plaza Sanitary & Storm Sewers Construction (70% Complete) |
| Location/ Description |
Roof drain disconnection and sewer separation at the Lincoln Street Plaza. |
| Activities | Storm and sanitary sewer construction between Lincoln St. and rear of the Plaza. Internal roof drain construction. Temporary restrictions (closures) to the east entrance of the plaza |
| Project- |
Public-Side Lead Service Replacement in the West Wartime Area (10% Complete) |
| Location/ Description |
Replacement of the public-side portion of lead water services at 43 addresses in the Dunkirk Road and Exeter Avenue Area |
| Activities | Construction underway. Road Closed during working hours. Intermittent water disruptions to individual affected properties. |
© 2012 The Corporation of The City of Welland
60 East Main Street, Welland, Ontario L3B 3X4 (905) 735-1700
Business Hours - Monday to Friday 8:30am - 4:30pm