CONSTRUCTION

All other road closures can be found under our road closure page.

Construction Activity for Municipal Subdivisions and Niagara Region Projects
for the week of April 14. 2014
Project-

Colborne Dog Park (60% Complete)

Location/
Description
Located at the end of Colborne Street. The project consists of a small dog park enclosure and a large dog park enclosure.
Activities Contractor started on Large Dog Park Enclosure last week.
Project-

Light Retrofitting Project for Museum Building (80% Complete)

Location/
Description
Retrofitting the existing lighting for the Museum Building.
Activities The contractor is working on the main level of the Museum this week.
Project-

Elevator Project for Museum Building (0% complete)

Location/
Description
Retrofitting the existing elevator for Museum Building to meet TSSA standards.
Activities To start on the project at the end of April, 2014
Project-

Standby Emergency Power Generator (0% Complete)

Location/
Description
Generator to be located on the top of the east side Civic Square Building
Activities Require further engineering evaluation for the generator for new gas line design due to the limited gas pressure. Looking at a generator that works on low gas pressure.
Project-

OAW Tunnel Disconnection and Sewer Separation (2% Complete)

Location/
Description
Sewer Construction between River Road and Salit Steel Property in the City of Welland.
Activities The contractor completed the clearing and grubbing of the bush on site last week. The consultant is redesigning the grades and alignment of the sewer.
Project-

Clare Estates 3 Phase 2 (40% complete)

Location/
Description
20 Lot Subdivision located at Webber Road and South Pelham
Activities Sanitary and Storm Sewer works have been completed. Watermain construction to be completed this month.
One lane of traffic open at all times
Project-

Dual Fuel Tank Work 2013 (99% completed)

Location/
Description
Installation of an aboveground Dual Fuel Tank for colour diesel and high octane fuel for the Municipal Service Yard.
Activities Contractor to start rectifying the deficiencies next week and complete them by mid-May.
Project-

Chippawa Park Pool Building Work 2013 (70% completed)

Location/
Description
Retrofitting the existing Pool Building into a year round Building for many events at Chippawa Park.
Activities To start on the roof, insulation and block walls for exterior works this week. To start on the bathroom fixtures and complete the interior walls this week.