HOME   •    TEXT VERSION   •    CONTACT US

CONSTRUCTION

construction graphic


All other road closures can be found under our road closure page.

Please check the Niagara Region's web site for additional road works in the Niagara Area.

 

Construction Activity for Municipal Subdivisions and Niagara Region Projects
for the week of February 15, 2016

Municipal Construction Projects:

Project-

Sidewalk Replacement Program Phase 1 (98% complete) Phase 2 (85% complete)

Location/
Description
To replace existing sidewalk bays in poor condition throughout the City. The contract has been extended to include additional areas in the City (Phase 2 Sidewalk Program)
Activities Replacing existing sidewalk bays throughout the City. 2015 Sidewalk Phase 2 Program to complete in April, 2016.
Project-

Empire Area Watermain Replacement and Sewer Separation (98% complete)

Location/
Description
To install watermain, watermain services and storm sewer for the Empire Area.
Activities Contractor to complete the deficiencies in early Spring.
Project-

Clare Estates Phase 4/5 Work on South Pelham (80% complete)

Location/
Description
Removed existing road surface, replace/upgrade/install new underground infrastructure for Clare Estates Phases and new Sparrow Meadows developments
Activities Underground work complete, curbs installed, base asphalt in place
Project-

Lincoln Street Sanitary Sewer Replacement (98% complete)

Location/
Description
Replacing the sanitary sewer for Lincoln Street from Mayfair to Verne Ave..
Activities To complete the deficiencies this week.
Project-

Clare Avenue Extension (65% complete)

Location/
Description
Clare Avenue extension between Lynbrook Lane and Webber Road for future development
Activities Various underground works, earth moving, grading. Watermain testing results received and passed. One watermain connection commissioned. Waiting for the schedule to complete the other watermain connection. Contractor to start on remaining works in early spring
Project-

Hansler Heights (Thorold) (60% complete)

Location/
Description
Various work being done on Hansler Road to accommodate new development in Thorold
Activities Underground infrastructure, road grading. Contractor to start on remaining works in early spring
Project-

Glenwood Park (0% Complete)

Location/
Description
Water Service for future water park.
Activities Installation of water service for park. To start in late February, 2016 or early March, 2016

 

Other Construction Projects:

Bridges Close For Improvements

Niagara Region will undertake a complete replacement of the Beaverdams Road Bridge (Located On Beaverdams Rd., Thorold) and the Power Canal Bridge (Located on Merrittville Hwy. Thorold) commencing on Monday, March 30, 2015 until August 2016. For more information please click here.