Construction Activity for Municipal Subdivisions and Niagara Region Projects
for the week of October 20, 2014
Project-

Utility Cuts Final Reinstatement 2014 (98% completed)

Location/
Description
Reinstating the utility cuts for the City of Welland.
Activities The contractor to complete the deficiencies and asphalt works by this week.
Project-

Plymouth Road and Churchill Ave. Reconstruction (45% Complete)

Location/
Description
To reconstruct the road for Plymouth Road from the Tracks to Lincoln and reconstruct the road for Churchill Ave. from Plymouth Road to approximately 200m east.
Activities The contractor is working on the road works this week.
One lane of traffic open at all times. There are disruptions to the pedestrians using the sidewalks from the tracks to Churchill while there is equipment working on the road.
Project-

Canal Bank, Shaw Street and Regatta Road Reconstruction Project 2014 (90% complete)

Location/
Description
To reconstruct the road for Canal Bank, built an entrance off of Shaw St. for the Flatwater Centre and sidewalk/surface works for Regatta Road.
Activities Contractor will be working on Regatta and Canal Bank Boulevards
The road will be closed this week for boulevard and line painting works.
Project-

Crack Sealing Program 2014 (95% complete)

Location/
Description
To crack seal the asphalt cracks for various street throughout the City of Welland.
Activities To start on the crack sealing of parking lots for Civic Square, WCWC, Arena and Courthouse by end of October, 2014..
Project-

Fitch Street Sewer/Road and First Avenue Urbanization Project 2014 (97% complete)

Location/
Description
To reconstruct the road for Fitch Street from PCD to First Ave. and urbanization First Ave. from Quaker Road to College Park Drive.
Activities Working on the boulevard works for First Avenue this week.
There may be disruption to the pedestrians using the sidewalk for First Avenue between Quaker and Woodgate Drive when the contractor is working on the boulevard works on First Avenue.
Project-

Sidewalk Replacement Program (0% complete)

Location/
Description
To replace existing sidewalk bays in poor condition throughout the City.
Activities To start the first week of November, 2014.
Project-

Lead Watermain Services Replacement (0% complete)

Location/
Description
Replacement of Lead Watermain Services for Riverside Drive.
Activities To start this project in the first week of December, 2014.
Project-

Scholfield Avenue Watermain Replacement (0% complete)

Location/
Description
To install watermain, watermain services and sanitary services for T/H block
Activities To start on this project on October 29, 2014.